Townhouses, 172 units
21200 Block of 83 Avenue
- Under review
- Approved in principle
- Approved
Council has given early approval (third reading). Conditions still have to be met. How approval works
The Township’s description
The applicant proposes to amend the Williams Neighbourhood Plan by revising policy 5.5.1 (4b) to require that four (4) parking spaces be required only where Rowhouse/Townhouse units front an arterial street, and to re-designate approximately 69.7m long strip of land 83 Avenue from Single-Family Mixed Residential to Rowhouse/Townhouse. Project also includes amendments to both the Official Community Plan from Suburban Residential Zone SR-2 to a yet to be determined Comprehensive Development Zone for the development of 172 townhouse units. Multi-family and GHG Development Permit applications have also been submitted.
- Building type
- Townhouses
- Project number
- 08-25-0120
- Year applied
- 2021
- Applications
- Development permit, Rezoning, OCP amendment
- Township status
- DP101269: Application received · RO100238: Council 3rd Reading: Passed
What this means
What the applicant is asking for
- Development permit: Sets how the buildings will look and sit on the site: design, landscaping and protecting trees and streams.
- Rezoning: Changes what the land can be used for and how much can be built on it.
- OCP amendment: Changes the Township’s long-term plan for the area (the Official Community Plan). Projects ask for this when they want more than the plan allows.
Where it is now
This project has conditional approval: Council gave the bylaw third reading (for a subdivision, the Township’s Approving Officer issued a preliminary approval). Before final approval, the developer still has to meet the conditions, such as a servicing agreement for roads and pipes, and paying development fees.
The file was opened in 2021, about 5 years ago. Half of the Township of Langley projects at this stage on our map were applied for in 2021 or earlier.
Around this project
There are 16 other active applications within 1 km: 14 under review, 2 approved in principle and 0 approved. 10 of them are for new homes (houses, townhouses or apartments).
Can you still have your say?
Mostly not. The public hearing or notice period has usually passed by this stage. You can still write to the Township, but big changes now are rare.